Team Name: Collaborative Science Platform
Date: 19.12.2023
This week,
Subteams:
- Front-end Team: Zülal, Bengisu, Abdullah, Mehmet, Ömer Faruk, Leyla
- Back-end Team: Ömer Şükrü, Ahmed Bera, Oğuz, Hakan, Arda, Ali Mert
Our objective for the following week,
Description | Issue | Assignee | Due | Estimated Duration | Actual Duration | PR |
---|---|---|---|---|---|---|
FE - Add Review Feature to Workspace Page | #596 | Mehmet, Zülal | 26.12.2023 | 8hr | 5hr | #644 |
FE - Privacy Policy to Login Page | #598 | Abdullah, Bengisu | 19.12.2023 | 1hr | 1hr | #618 |
FE - Admin Features | #565 | Abdullah, Bengisu | 19.12.2023 | 8hr | 10hr | #629 |
FE - Annotation Implementation | #565 | Leyla, Ömer Faruk | 19.12.2023 | 10hr | 8hr | #634 |
BE - Workspace API Update | #600 | Hakan | 19.12.2023 | 8hr | ||
FE - Enhancements for Workspace Page | #602 | Zülal | 19.12.2023 | 2hr | 2hr | #643 |
BE - Annotations Implementation | #603 | Ömer Şükrü, Ahmed Bera | 19.12.2023 | 5hr | 6hr | #639, #636, #616 |
BE - E-Mail Notification Implementation | #605 | Ali Mert | 19.12.2023 | 4hr | 5hr | #623 |
BE - API Update for Filtering | #608 | Arda | 19.12.2023 | 2hr | 2hr | #627 |
BE - ORCID Integration | #607 | Arda | 19.12.2023 | 2hr | 2hr | #626 |
Node GET API Update | #599 | Arda | 19.12.2023 | 2hr | 1hr | #617 |
Description | Issue | Assignee | PR |
---|---|---|---|
Swagger UI Implementation | #578 | Hakan | #579 |
Security Update For the APIs | - | Hakan | #587 |
BE - Reviewer Randomizer and Assigner | #581 | Ahmed Bera | #586 |
BE - Create Question API - Modification | #593 | Arda | #594 |
FE - Create Workspace from a Node | #611 | Zülal | #642 |
We encounter some problem in #588. This PR was closed and the work was carried to another PR, #610, with some additional tasks. Semantic tags couldnt be added to workspaces since some additional APIs were needed.
Admin features connection to backend is delayed due to some updates on related APIs. After it is deployed we will connect admin features to backend. Also hide/show question/answer part is not implemented since question answer features is just merged to the frontend branch. We will complete the task soon since everything needed is ready now.
Description | Issue | Assignee | Due | Estimated Duration |
---|---|---|---|---|
FE - Add Review Feature to Workspace Page | #596 | Mehmet, Zülal | 26.12.2023 | 6hr |
FE - Add semantic tags (Workspace and User Profile) | #648 | Mehmet | 26.12.2023 | 5hr |
- Ahmed Bera Pay
- Ahmet Abdullah Susuz
- Ali Mert Geben
- Arda Arslan
- Bengisu Kübra Takkin
- Hakan Emre Aktaş
- Leyla Yayladere
- Mehmet Süzer
- Ömer Faruk Ünal
- Ömer Şükrü Uyduran
- Zülal Molla
🏠 Home
- Hakan Emre Aktas
- Ahmed Bera Pay
- Ömer Şükrü Uyduran
- Mehmet Süzer
- Ahmet Abdullah Susuz
- Ali Mert Geben
- Oğuz Pançuk
- Arda Arslan
- Zülal Molla
- Leyla Yayladere
- Omer Faruk Unal
- Bengisu Kübra Takkin
451 Weekly Progress Reports
- Progress Report #1 | 03.10.2023
- Progress Report #2 | 10.10.2023
- Progress Report #3 | 17.10.2023
- Progress Report #4 | 24.10.2023
- Progress Report #5 | 07.11.2023
- Progress Report #6 | 14.11.2023
- Progress Report #7 | 21.11.2023
- Progress Report #8 | 05.12.2023
- Progress Report #9 | 12.12.2023
- Progress Report #10 | 19.12.2023
352 Meeting Notes
- Meeting #1 | 08.03.2023
- Meeting #2 | 13.03.2023
- Meeting #3 | 15.03.2023
- Meeting #4 | 22.03.2023
- Meeting #5 | 24.03.2023
- Meeting #6 | 30.03.2023
- Meeting #7 | 05.04.2023
- Meeting #8 | 07.04.2023
- Meeting #9 | 19.04.2023
- Meeting #10 | 27.04.2023
- Meeting #11 | 03.05.2023
- Meeting #12 | 06.05.2023
- Meeting #13 | 08.05.2023
- Meeting #14 | 10.05.2023
- CmpE451 Customer Milestone 1 Report
- CmpE451 Customer Milestone 2 Report
- CmpE451 Final Milestone Report