Adding Links for Tasks
ZeeshanShafqat edited this page Jan 24, 2014
·
3 revisions
###VSTO To link a task using VSTO:
- Create a new project in Visual Studio.
- In the Solution Explorer, right-click and select Add Reference.
- Select the COM components tab, and select Microsoft Project 12.0 Object Library.
- Click OK.
This imports the Microsoft.Office.Interop.MSProject namespace at the start of your code. Use the code from the following example to link tasks.
//Create an Application object
Microsoft.Office.Interop.MSProject.Application projectApplication = new MSProject.Application();
object missingValue = System.Reflection.Missing.Value;
//Open an MPP file
projectApplication.FileOpenEx("Project.mpp",
missingValue, missingValue, missingValue, missingValue,
missingValue, missingValue, missingValue, missingValue,
missingValue, missingValue, PjPoolOpen.pjPoolReadOnly,
missingValue, missingValue, missingValue, missingValue,
missingValue);
//Create a Project object by assigning active project
Microsoft.Office.Interop.MSProject.Project project = projectApplication.ActiveProject;
//Add dependencies among the tasks
project.Tasks.get_UniqueID(2).TaskDependencies.Add(project.Tasks.get_UniqueID(1), PjTaskLinkType.pjFinishToStart);
project.Tasks.get_UniqueID(3).TaskDependencies.Add(project.Tasks.get_UniqueID(2), PjTaskLinkType.pjFinishToStart);
project.Tasks.get_UniqueID(4).TaskDependencies.Add(project.Tasks.get_UniqueID(3), PjTaskLinkType.pjFinishToStart);
project.Tasks.get_UniqueID(5).TaskDependencies.Add(project.Tasks.get_UniqueID(4), PjTaskLinkType.pjFinishToStart);
project.Tasks.get_UniqueID(5).TaskDependencies.Add(project.Tasks.get_UniqueID(2), PjTaskLinkType.pjFinishToStart);
//Display the dependencies
foreach (Task tsk in project.Tasks)
{
foreach (TaskDependency dep in project.Tasks.get_UniqueID(tsk.ID).TaskDependencies)
{
Console.WriteLine("From ID = " + dep.From.ID + "=>To ID = " + dep.To.ID);
}
Console.WriteLine("____________________________________________________________");
}
//Save the project
projectApplication.FileCloseAll(Microsoft.Office.Interop.MSProject.PjSaveType.pjSave);
###Aspose.Tasks
To link tasks in a project using Aspose.Tasks for .NET:
- Create a new project in Visual Studio.
- In the Solution Explorer, right-click and select Add Reference.
- Select .NET tab and select Aspose.Tasks.
- Click OK.
This imports the Aspose.Tasks namespace at the start of your code. Use the code from the following example to link tasks.
//Load a project
ProjectReader rdr = new ProjectReader();
FileStream St = new FileStream("Project.mpp", FileMode.Open);
Project prj = rdr.Read(St);
St.Close();
//Link the tasks
TaskLink tsklnk = new TaskLink(prj.RootTask.Children[0] as Aspose.Tasks.Task, prj.RootTask.Children[1] as Aspose.Tasks.Task, TaskLinkType.FinishToStart);
prj.AddTaskLink(tsklnk);
tsklnk = new TaskLink(prj.RootTask.Children[1] as Aspose.Tasks.Task, prj.RootTask.Children[2] as Aspose.Tasks.Task, TaskLinkType.FinishToStart);
prj.AddTaskLink(tsklnk);
tsklnk = new TaskLink(prj.RootTask.Children[2] as Aspose.Tasks.Task, prj.RootTask.Children[3] as Aspose.Tasks.Task, TaskLinkType.FinishToStart);
prj.AddTaskLink(tsklnk);
tsklnk = new TaskLink(prj.RootTask.Children[3] as Aspose.Tasks.Task, prj.RootTask.Children[4] as Aspose.Tasks.Task, TaskLinkType.FinishToStart);
prj.AddTaskLink(tsklnk);
tsklnk = new TaskLink(prj.RootTask.Children[1] as Aspose.Tasks.Task, prj.RootTask.Children[4] as Aspose.Tasks.Task, TaskLinkType.FinishToStart);
prj.AddTaskLink(tsklnk);
//Display links among the tasks
ArrayList allinks = new ArrayList(prj.TaskLinks);
foreach (TaskLink tasklnk in allinks)
{
Console.WriteLine("From ID = " + tasklnk.PredTask.Id + "=>To ID = " + tasklnk.SuccTask.Id);
Console.WriteLine("________________________________________");
}
//Save the project
prj.Save("Project1.mpp", Aspose.Tasks.Saving.SaveFileFormat.MPP);