[Roadmap] 前端产品化:七项交付任务与并行安排 #257
Copy link
Copy link
Open
7 / 77 of 7 issues completedLabels
epicParent issue grouping related deliverablesParent issue grouping related deliverablesjavascriptPull requests that update javascript codePull requests that update javascript coderoadmapProduct roadmap and cross-cutting delivery trackingProduct roadmap and cross-cutting delivery tracking
Description
Activity
- addedjavascriptPull requests that update javascript codePull requests that update javascript coderoadmapProduct roadmap and cross-cutting delivery trackingProduct roadmap and cross-cutting delivery trackingepicParent issue grouping related deliverablesParent issue grouping related deliverables
on Oct 5, 2026 - added sub-issues
on Oct 5, 2026 - removed a sub-issue
on Oct 5, 2026 - changed the title
[-][Roadmap] 前端产品化:可靠对话、主工作区与开发交付流程[/-][+][Roadmap] 前端产品化:七项交付任务与并行安排[/+]on Oct 5, 2026
Metadata
Metadata
Assignees
Labels
epicParent issue grouping related deliverablesParent issue grouping related deliverablesjavascriptPull requests that update javascript codePull requests that update javascript coderoadmapProduct roadmap and cross-cutting delivery trackingProduct roadmap and cross-cutting delivery tracking
将已有能力连成日常开发流程:接入项目与模型 → 连续对话 → 检查文件和改动 → 运行验证 → 提交交付。
本路线图保留 1 个总 issue + 7 个交付任务,使用两层原生父子关系。一个 issue 对应一个可验收结果,可以由多个小 PR 完成;前后端步骤和内部依赖写入任务清单。
任务与并行安排
首轮建议同步推进正确性、模型接入、会话性能和独立工作区组件;后端有可用人力时同步开发搜索或应用预览。
阻塞与合并协调
唯一跨任务交付依赖为 #258 → #259:完整工作区交付验收需要批次能力修复。该关系不阻止文件/终端组件提前开发。原文件→回复、API→UI 的先后关系已收进各任务内部清单。
app.tsx/conversation.tsx 的修改保持局部;#259 与 #260 约定来源身份和渲染边界,共用一次 PlanDeliveryPanel 提取。后端任务在最新 OpenAPI 上生成客户端,按小 PR 合并。共享文件需要协调,不另设人为阻塞。
完成标准
每个任务按自己的行为标准验收,完成后关闭;仅运行受影响检查和已有适用 CI。继续复用草稿恢复、消息队列、计划、审批、Git/PR 与 Inspector,保留官方完整 TTF 约定和已有 Monaco 按需加载。
调查基线为 main
dab1e2b6(2026-10-05),来自代码、模块调查、本地生产界面与一次通过的生产构建。本路线图中的工作尚待实施。整理记录
原有 13 个过细条目已归并并关闭为“被替代”,保留原始说明和转向链接。关闭这些条目不代表相关功能已经完成。