Notifications
You must be signed in to change notification settings - Fork 0
Expand file tree
/
Copy path03_create_analysis_views.sql
More file actions
173 lines (167 loc) · 6.71 KB
/
Copy path03_create_analysis_views.sql
File metadata and controls
173 lines (167 loc) · 6.71 KB
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
-- Construction Project Controls Analytics
-- Analyze Phase: analytical views for SQLite
DROP VIEW IF EXISTS vw_latest_monthly_performance;
CREATE VIEW vw_latest_monthly_performance AS
WITH ranked AS (
SELECT
mp.*,
ROW_NUMBER() OVER (
PARTITION BY mp.Project_ID
ORDER BY date(mp.Reporting_Date) DESC
) AS rn
FROM monthly_performance mp
)
SELECT *
FROM ranked
WHERE rn = 1;
DROP VIEW IF EXISTS vw_change_order_summary;
CREATE VIEW vw_change_order_summary AS
SELECT
Project_ID,
COUNT(*) AS CO_Count,
SUM(CASE WHEN Change_Status = 'Approved' THEN 1 ELSE 0 END) AS Approved_CO_Count,
SUM(CASE WHEN Change_Status = 'Approved' THEN COALESCE(Approved_Value, 0) ELSE 0 END) AS Total_Approved_CO_Value,
SUM(CASE WHEN Change_Status = 'Pending' THEN COALESCE(Submitted_Value, 0) ELSE 0 END) AS Total_Pending_CO_Value,
SUM(CASE WHEN Change_Status = 'Approved' THEN Schedule_Impact_Days ELSE 0 END) AS Approved_CO_Schedule_Days,
AVG(CASE
WHEN Change_Status = 'Approved' AND Approved_Date IS NOT NULL
THEN julianday(Approved_Date) - julianday(Submitted_Date)
END) AS Avg_CO_Approval_Days
FROM change_orders
GROUP BY Project_ID;
DROP VIEW IF EXISTS vw_rfi_summary;
CREATE VIEW vw_rfi_summary AS
SELECT
Project_ID,
COUNT(*) AS RFI_Count,
SUM(CASE WHEN RFI_Status = 'Open' THEN 1 ELSE 0 END) AS Open_RFI_Total,
AVG(Response_Days) AS Avg_RFI_Response_Days,
SUM(CASE
WHEN Response_Date IS NOT NULL
AND date(Response_Date) > date(Required_Response_Date)
THEN 1 ELSE 0 END) AS Late_RFI_Count,
SUM(CASE WHEN Cost_Impact > 0 OR Schedule_Impact_Days > 0 THEN 1 ELSE 0 END) AS Impacted_RFI_Count,
SUM(Cost_Impact) AS Total_RFI_Cost_Impact,
SUM(Schedule_Impact_Days) AS Total_RFI_Schedule_Days
FROM rfi_log
GROUP BY Project_ID;
DROP VIEW IF EXISTS vw_project_performance_analysis;
CREATE VIEW vw_project_performance_analysis AS
SELECT
p.Project_ID,
p.Project_Name,
p.Project_Type,
p.City,
p.State,
p.Client_Type,
p.Contract_Type,
p.Delivery_Method,
p.Project_Manager_ID,
p.Project_Status,
p.Current_Phase,
l.Reporting_Date AS Latest_Reporting_Date,
p.Original_Budget,
p.Current_Budget,
p.Original_Contingency,
l.Planned_Value,
l.Earned_Value,
l.Actual_Cost,
l.Committed_Cost,
p.Percent_Complete,
p.Planned_End_Date,
p.Forecast_End_Date,
l.Contingency_Used,
l.Open_RFI_Count AS Latest_Open_RFI_Count,
COALESCE(co.CO_Count, 0) AS CO_Count,
COALESCE(co.Approved_CO_Count, 0) AS Approved_CO_Count,
COALESCE(co.Total_Approved_CO_Value, 0) AS Total_Approved_CO_Value,
COALESCE(co.Total_Pending_CO_Value, 0) AS Total_Pending_CO_Value,
COALESCE(co.Approved_CO_Schedule_Days, 0) AS Approved_CO_Schedule_Days,
co.Avg_CO_Approval_Days,
COALESCE(r.RFI_Count, 0) AS RFI_Count,
COALESCE(r.Open_RFI_Total, 0) AS Open_RFI_Total,
r.Avg_RFI_Response_Days,
COALESCE(r.Late_RFI_Count, 0) AS Late_RFI_Count,
COALESCE(r.Impacted_RFI_Count, 0) AS Impacted_RFI_Count,
COALESCE(r.Total_RFI_Cost_Impact, 0) AS Total_RFI_Cost_Impact,
COALESCE(r.Total_RFI_Schedule_Days, 0) AS Total_RFI_Schedule_Days,
CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0) AS CPI,
CAST(l.Earned_Value AS REAL) / NULLIF(l.Planned_Value, 0) AS SPI,
l.Earned_Value - l.Actual_Cost AS Cost_Variance,
l.Earned_Value - l.Planned_Value AS Schedule_Variance,
p.Original_Budget /
NULLIF(CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0), 0) AS EAC,
(
p.Original_Budget /
NULLIF(CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0), 0)
) - l.Actual_Cost AS ETC,
p.Original_Budget - (
p.Original_Budget /
NULLIF(CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0), 0)
) AS VAC,
(
(
p.Original_Budget /
NULLIF(CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0), 0)
) - p.Original_Budget
) / NULLIF(p.Original_Budget, 0) AS Forecast_Overrun_Pct,
CAST(p.Current_Budget - p.Original_Budget AS REAL) /
NULLIF(p.Original_Budget, 0) AS Cost_Growth_Pct,
CAST(julianday(p.Forecast_End_Date) - julianday(p.Planned_End_Date) AS INTEGER)
AS Schedule_Delay_Days,
CAST(COALESCE(co.Total_Approved_CO_Value, 0) AS REAL) /
NULLIF(p.Original_Budget, 0) AS Approved_CO_Pct,
CAST(COALESCE(co.Total_Pending_CO_Value, 0) AS REAL) /
NULLIF(p.Original_Budget, 0) AS Pending_CO_Pct,
CAST(l.Contingency_Used AS REAL) /
NULLIF(p.Original_Contingency, 0) AS Contingency_Utilization_Pct,
(
CAST(l.Contingency_Used AS REAL) /
NULLIF(p.Original_Contingency, 0)
) / NULLIF(p.Percent_Complete / 100.0, 0) AS Contingency_Burn_Ratio,
CAST(COALESCE(r.Late_RFI_Count, 0) AS REAL) /
NULLIF(COALESCE(r.RFI_Count, 0), 0) AS Late_RFI_Rate,
CASE
WHEN (
CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0) < 0.90
OR CAST(l.Earned_Value AS REAL) / NULLIF(l.Planned_Value, 0) < 0.90
OR (
(
p.Original_Budget /
NULLIF(CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0), 0)
) - p.Original_Budget
) / NULLIF(p.Original_Budget, 0) > 0.10
OR julianday(p.Forecast_End_Date) - julianday(p.Planned_End_Date) > 30
OR CAST(l.Contingency_Used AS REAL) /
NULLIF(p.Original_Contingency, 0) > 0.90
OR (
CAST(l.Contingency_Used AS REAL) /
NULLIF(p.Original_Contingency, 0)
) / NULLIF(p.Percent_Complete / 100.0, 0) > 1.50
) THEN 'Red'
WHEN (
CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0) < 0.95
OR CAST(l.Earned_Value AS REAL) / NULLIF(l.Planned_Value, 0) < 0.95
OR (
(
p.Original_Budget /
NULLIF(CAST(l.Earned_Value AS REAL) / NULLIF(l.Actual_Cost, 0), 0)
) - p.Original_Budget
) / NULLIF(p.Original_Budget, 0) > 0.05
OR julianday(p.Forecast_End_Date) - julianday(p.Planned_End_Date) > 15
OR CAST(l.Contingency_Used AS REAL) /
NULLIF(p.Original_Contingency, 0) > 0.75
OR (
CAST(l.Contingency_Used AS REAL) /
NULLIF(p.Original_Contingency, 0)
) / NULLIF(p.Percent_Complete / 100.0, 0) > 1.20
) THEN 'Yellow'
ELSE 'Green'
END AS Health_Status
FROM projects p
JOIN vw_latest_monthly_performance l
ON l.Project_ID = p.Project_ID
LEFT JOIN vw_change_order_summary co
ON co.Project_ID = p.Project_ID
LEFT JOIN vw_rfi_summary r
ON r.Project_ID = p.Project_ID;